AMS Design Submission | 2008-12-01 | 2008-12-01 (17:00) | 1d | |||
AMS Manufacture | 2008-12-01 (18:00) | 2009-03-02 (17:00) | 65d | |||
IMS Test Board & Software | 2008-12-01 (18:00) | 2009-01-12 (17:00) | 30d | |||
Wire bonding | 2009-03-02 (18:00) | 2009-03-09 (17:00) | 5d | |||
Acceptance Testing | 2009-03-09 (18:00) | 2009-04-06 (17:00) | 20d | |||
System Components Available | 2009-04-06 (18:00) | 2009-04-07 (17:00) | 1d | |||
Systems Integration | 2009-04-07 (18:00) | 2009-07-07 (17:00) | 65d | |||
Functional Tests | 2009-07-07 (18:00) | 2009-09-29 (17:00) | 60d | |||
Test Review 1 | 2009-09-29 (18:00) | 2009-09-30 (17:00) | 1d | |||
System Commissioning | 2009-09-30 (18:00) | 2009-12-23 (17:00) | 60d | |||
Design Modifications | 2009-07-07 (18:00) | 2009-12-29 (17:00) | 125d | |||
Design Review 4 | 2009-12-29 (18:00) | 2009-12-30 (17:00) | 1d | |||
Layout | 2009-12-30 (18:00) | 2010-02-24 (17:00) | 40d | |||
Layout Verification | 2010-02-24 (18:00) | 2010-03-31 (17:00) | 25d | |||
Design Review 5 | 2010-03-31 (18:00) | 2010-04-01 (17:00) | 1d | |||
Final Design | 2010-04-01 (18:00) | 2010-05-06 (17:00) | 25d | |||
Design Review 6 | 2010-05-06 (18:00) | 2010-05-07 (17:00) | 1d | |||
Preparation for submission | 2010-05-07 (18:00) | 2010-06-04 (17:00) | 20d | |||
AMS Design Submission 2 | 2010-06-04 (18:00) | 2010-06-07 (17:00) | 1d | |||
AMS Manufacture 2 | 2010-06-07 (18:00) | 2010-09-06 (17:00) | 65d | |||
Wire bonding 2 | 2010-09-06 (18:00) | 2010-09-13 (17:00) | 5d | |||
Acceptance testing 2 | 2010-09-13 (18:00) | 2010-10-18 (17:00) | 25d | |||
Systems Integration 2 | 2010-09-13 (18:00) | 2010-10-11 (17:00) | 20d | |||
Functional Tests 2 | 2010-10-11 (18:00) | 2011-01-17 (17:00) | 70d | |||
Test Review 2 | 2011-01-17 (18:00) | 2011-01-18 (17:00) | 1d | |||
System Commissioning 2 | 2011-01-18 (18:00) | 2011-04-26 (17:00) | 70d | |||
DSSD: Prototypes available | 2009-05-01 | 2009-05-01 (17:00) | 1d | Tue 11 Nov 2008, 18:43 | ||
DSSD: Commissioning tests | 2009-05-01 (18:00) | 2009-05-29 (17:00) | 20d | |||
GSI: Commissioning | 2009-06-01 | 2009-07-24 (17:00) | 40d | |||
FEE: Prototypes available | 2009-04-07 (18:00) | 2009-04-08 (17:00) | 1d |