Milestone | Date | Notes |
---|
Name | Progress | Start | End | Work | Resources | Notes |
---|---|---|---|---|---|---|
AMS Design Submission | 0% | 2008-12-01 | 2008-12-01 (17:00) | 1d | ||
AMS Manufacture | 0% | 2008-12-01 (18:00) | 2009-03-02 (17:00) | 65d | ||
IMS Test Board & Software | 0% | 2008-12-01 (18:00) | 2009-01-12 (17:00) | 30d | ||
Wire bonding | 0% | 2009-03-02 (18:00) | 2009-03-09 (17:00) | 5d | ||
Acceptance Testing | 0% | 2009-03-09 (18:00) | 2009-04-06 (17:00) | 20d | ||
System Components Available | 0% | 2009-04-06 (18:00) | 2009-04-07 (17:00) | 1d | ||
Systems Integration | 0% | 2009-04-07 (18:00) | 2009-07-07 (17:00) | 65d | ||
Functional Tests | 0% | 2009-07-07 (18:00) | 2009-09-29 (17:00) | 60d | ||
Test Review 1 | 0% | 2009-09-29 (18:00) | 2009-09-30 (17:00) | 1d | ||
System Commissioning | 0% | 2009-09-30 (18:00) | 2009-12-23 (17:00) | 60d | ||
Design Modifications | 0% | 2009-07-07 (18:00) | 2009-12-29 (17:00) | 125d | ||
Design Review 4 | 0% | 2009-12-29 (18:00) | 2009-12-30 (17:00) | 1d | ||
Layout | 0% | 2009-12-30 (18:00) | 2010-02-24 (17:00) | 40d | ||
Layout Verification | 0% | 2010-02-24 (18:00) | 2010-03-31 (17:00) | 25d | ||
Design Review 5 | 0% | 2010-03-31 (18:00) | 2010-04-01 (17:00) | 1d | ||
Final Design | 0% | 2010-04-01 (18:00) | 2010-05-06 (17:00) | 25d | ||
Design Review 6 | 0% | 2010-05-06 (18:00) | 2010-05-07 (17:00) | 1d | ||
Preparation for submission | 0% | 2010-05-07 (18:00) | 2010-06-04 (17:00) | 20d | ||
AMS Design Submission 2 | 0% | 2010-06-04 (18:00) | 2010-06-07 (17:00) | 1d | ||
AMS Manufacture 2 | 0% | 2010-06-07 (18:00) | 2010-09-06 (17:00) | 65d | ||
Wire bonding 2 | 0% | 2010-09-06 (18:00) | 2010-09-13 (17:00) | 5d | ||
Acceptance testing 2 | 0% | 2010-09-13 (18:00) | 2010-10-18 (17:00) | 25d | ||
Systems Integration 2 | 0% | 2010-09-13 (18:00) | 2010-10-11 (17:00) | 20d | ||
Functional Tests 2 | 0% | 2010-10-11 (18:00) | 2011-01-17 (17:00) | 70d | ||
Test Review 2 | 0% | 2011-01-17 (18:00) | 2011-01-18 (17:00) | 1d | ||
System Commissioning 2 | 0% | 2011-01-18 (18:00) | 2011-04-26 (17:00) | 70d | ||
DSSD: Prototypes available | 0% | 2009-05-01 | 2009-05-01 (17:00) | 1d | Tue 11 Nov 2008, 18:43 | |
DSSD: Commissioning tests | 0% | 2009-05-01 (18:00) | 2009-05-29 (17:00) | 20d | ||
GSI: Commissioning | 0% | 2009-06-01 | 2009-07-24 (17:00) | 40d | ||
FEE: Prototypes available | 0% | 2009-04-07 (18:00) | 2009-04-08 (17:00) | 1d |
Name | Type | Tasks |
---|