Start Date: 2008-11-11
End Date: 2011-04-26
Duration: 896d 17h
Report Date: 2008-11-11

Simplified Gantt Chart


*** Note: Gantt chart requires CSS capability. ***
Task Schedule
Dates:
11 Nov 2008 26 Apr 2011
AMS Design Submission
AMS Manufacture
IMS Test Board & Software
Wire bonding
Acceptance Testing
System Components Available
Systems Integration
Functional Tests
Test Review 1
System Commissioning
Design Modifications
Design Review 4
Layout
Layout Verification
Design Review 5
Final Design
Design Review 6
Preparation for submission
AMS Design Submission 2
AMS Manufacture 2
Wire bonding 2
Acceptance testing 2
Systems Integration 2
Functional Tests 2
Test Review 2
System Commissioning 2
DSSD: Prototypes available
DSSD: Commissioning tests
GSI: Commissioning
FEE: Prototypes available

Project Milestones

Milestone Date Notes

Tasks

Name Progress Start End Work Resources Notes
AMS Design Submission 0% 2008-12-01 2008-12-01 (17:00) 1d
AMS Manufacture 0% 2008-12-01 (18:00) 2009-03-02 (17:00) 65d
IMS Test Board & Software 0% 2008-12-01 (18:00) 2009-01-12 (17:00) 30d
Wire bonding 0% 2009-03-02 (18:00) 2009-03-09 (17:00) 5d
Acceptance Testing 0% 2009-03-09 (18:00) 2009-04-06 (17:00) 20d
System Components Available 0% 2009-04-06 (18:00) 2009-04-07 (17:00) 1d
Systems Integration 0% 2009-04-07 (18:00) 2009-07-07 (17:00) 65d
Functional Tests 0% 2009-07-07 (18:00) 2009-09-29 (17:00) 60d
Test Review 1 0% 2009-09-29 (18:00) 2009-09-30 (17:00) 1d
System Commissioning 0% 2009-09-30 (18:00) 2009-12-23 (17:00) 60d
Design Modifications 0% 2009-07-07 (18:00) 2009-12-29 (17:00) 125d
Design Review 4 0% 2009-12-29 (18:00) 2009-12-30 (17:00) 1d
Layout 0% 2009-12-30 (18:00) 2010-02-24 (17:00) 40d
Layout Verification 0% 2010-02-24 (18:00) 2010-03-31 (17:00) 25d
Design Review 5 0% 2010-03-31 (18:00) 2010-04-01 (17:00) 1d
Final Design 0% 2010-04-01 (18:00) 2010-05-06 (17:00) 25d
Design Review 6 0% 2010-05-06 (18:00) 2010-05-07 (17:00) 1d
Preparation for submission 0% 2010-05-07 (18:00) 2010-06-04 (17:00) 20d
AMS Design Submission 2 0% 2010-06-04 (18:00) 2010-06-07 (17:00) 1d
AMS Manufacture 2 0% 2010-06-07 (18:00) 2010-09-06 (17:00) 65d
Wire bonding 2 0% 2010-09-06 (18:00) 2010-09-13 (17:00) 5d
Acceptance testing 2 0% 2010-09-13 (18:00) 2010-10-18 (17:00) 25d
Systems Integration 2 0% 2010-09-13 (18:00) 2010-10-11 (17:00) 20d
Functional Tests 2 0% 2010-10-11 (18:00) 2011-01-17 (17:00) 70d
Test Review 2 0% 2011-01-17 (18:00) 2011-01-18 (17:00) 1d
System Commissioning 2 0% 2011-01-18 (18:00) 2011-04-26 (17:00) 70d
DSSD: Prototypes available 0% 2009-05-01 2009-05-01 (17:00) 1d Tue 11 Nov 2008, 18:43
DSSD: Commissioning tests 0% 2009-05-01 (18:00) 2009-05-29 (17:00) 20d
GSI: Commissioning 0% 2009-06-01 2009-07-24 (17:00) 40d
FEE: Prototypes available 0% 2009-04-07 (18:00) 2009-04-08 (17:00) 1d

Resources

Name Type Email Tasks