AIDA Meeting - STFC RAL 14 March 2011 --------------------------------------- Present: SLT (by phone), IL, PCS, MK, RDP, JS Apologies: Summary of meeting ------------------ ASIC ---- Paul Booker 1h/mezzanine glueing/assembly/curing + bonding i.e ~6/day 3 delivered request 2-5 asap SLT to check further delivery of 20 ASIC mezzanines @ +3 weeks SLT to check further delivery of 20 ASIC mezzanines @ +6 weeks i.e. complete AIDA (cf. LYCCA) complement by early May Packaged devices delayed by other work. Plan to have packaged devices and tests performed April. FEE --- Mos - ~0.5 day basic commissioning tests per FEE64 2 pre + 6 production FEE64s delivered 7 operational + 1 with manufacturing/assembly issue probably requiring re-work sampling ADC buffer to be replaced with higher current/slower device to avoid oscillations evident in production devices - requesting quote for re-work of all production FEE64s PCS pursuing problems with ExceptionPCB deliveries and knock-on effects to Jaltek. At the moment, expect 78 PCBs DAQ/software ------------ Mechanical Design ----------------- Commissioning Tests ------------------- Other ----- TD/RDP to provide sampling ADC wish list Next meeting: 13.30 Wed 13 April