AIDA Meeting - STFC RAL 3 October 2011 -------------------------------------- Present: SLT, PCS, Mos, RDP, VFEP, JS, IL Apologies: PM Summary of meeting ------------------ Commissioning Tests ------------------- ... verbal summary of Aug 16-18 test ASIC ---- cf. 21.7.11 + 1 (+ 1 rework available) IL pointed that LYCCA may need entire requirement for 2012/Q2 Consensus was that we should aim to complete larger batch with dedicated week (@~5/day) by end of 2011. SLT will discuss scheduling with Paul Booker (RAL). PCS will forward LYCCA mezzanine PCBs and Cu to SLT/RAL. FEE --- ~50 tested OK ~20 to be tested ~7-8 with faults to be checked by Mos McB delivery problems. PCS expects to start work next week. This task is oncritical path to assembling multi-module, cooled system within racks. DAQ/software ------------ 2x FEE64 system operational with web/XML interface @ DL s/w runs in parallel SCL to work on merge & conversion to MBS event format Mechanical Design ----------------- System crates in assembly T4 Still awaiting progress on mech assbly frame at Liverpool - JS purusing this with local management. Other ----- Next meeting: 10.30 Thursday 17 November